Projects

Wyangala Dam, NSW

Project Summary

Supercity primarily engaged to provide core drilling for chute wall extensions.

  • Date:   2010
  • Location: Wyangala Dam, NSW
  • Client: Reed Construction Group
  • Contractor: REED Group
  • Services utilised: Core Drilling, Sawing.
  • The Project
    Super City Concrete Cutting were engaged by Reed Group for the Wyangala Dam NSW Stage 1B Spillway Chute Wall Raising Project, during March and April 2010. Super City’s involvement was in fixed sump lump sum works primarily in core drilling large quantities of holes up to 60mm diameter to depths of up to 1000mm for placement of starter bars for the chute wall extensions either side of the Wyangala Dam Spillway.
    The work was difficult in nature due to all works being at heights from 6m to 15m from the spillway slab, with the main access via boom lift or scissor lift.
Download Case Study

Testimonial